Reconnaissance study on the resources of infrastructure and raw materials were conducted in January 2010.
Tendering process for machinery supplies was commenced in May 2010.
The seven-mile access road from MeikhtilaTaunggyi Highway Road to plant area was completed.
Ground clearing and excavation for the factory area was undertaken in June 2010.
Memorandum of Agreement signing events for machinery supplies and technical services took place in October 2010.