Reconnaissance study on the resources of infrastructure and raw materials were conducted in January 2010. Tendering process for machinery supplies ....
• The agreement for the machine supply and construction of 1500 ton per day clinker production plant was signed between ....
• Kubyin weir and two reservoirs, upper dam and lower dam with the total storage capacity of 6 million gallons ....
• Mechanical installation was completed in November 2013. • The commission for the plant was commenced in December 2013 with ....
• Plant commissioning successfully completed in January 2014. • Apache Brand was launched in early ....